CONTRACTOR_QUESTIONS_30_MAY.PDF
Published: 06/01/2018
Description
Questions and the answers to those questions from contractor/s for the Kanopolis Trash Racks project a) Drawing SC100 and SC101 is sufficient to fabricate from is it really necessary to submit shop drawings? FRS Response: Yes, shop drawings ...