36C10F18R0556 0005 RFI FORM QUESTIONS AND RESPONSES SUMMARY 9-21-18 .PDF
Published: 09/21/2018
Description
Project NVAMC Perry Point CLC Construction Project Project N512-173 RFI NO. SECTI ON DRAWING# DESCRIPTION AMENDMENT/ POST DATE COMMENTS 018 X Fuel oil tank schedule required a 20k Fireguard but Fuel oil piping control schedule Sequence requires...