ADDENDUM_1.PDF
Published: 11/06/2018
Description
Addendum 1 Repair Runway 06/24 - NAAF SBML 12-1110 Charleston Air Force Base South Carolina 6 Nov 2018 1. For Clarification, there are 90 days for submittals and mobilization and 106 days for construction (including inclement weather)...