CT HITE OPERATIONAL PLAN MASTER SCHEDULE
Published: 11/16/2010
Description
ID Task Name Duration Start Finish 1 Program Management 1027 days Mon 10/4/10 Tue 9/9/14 2 Program Management Office Set Up 20 days Mon 10/4/10 Fri 10/29/10 3 Program Cehckpoints Preparation 850 days Mon 11/1/10 Fri 1/31/14 4 Program Checkpoints 9...