SMN SCHEDULE (PDF)
Published: 06/05/2019
Description
ID Task Mode Task Name Duration Start Finish 1 Salmon RCLT/AWOS?Tower Replacement Project 65 days Mon 7/1/19 Fri 9/27/19 2 Contract Award 0 days Mon 7/1/19 Mon 7/1/19 3 Contract Approval 4 wks Mon 7/1/19 Fri 7/26/19 4 Work Schedule 2 wks Mon 7/...