AMENDMENT 5 - RFI RESPONSES V2
Published: 09/23/2019
Description
Building_247_RFIs_and_Responses_V2.docx W912TF-19-Q-5024 – Building 247 Furniture RFIs September 13, 2019 Q: What is the deadline? A: 90 days preferred ADC Q: Will the vendors be required to hook up electrical? A: It is the intent of th...