BID RFIS - 503-19-112 REPLACE STEAM PROJECT.PDF
Published: 07/21/2023
Description
# Question AE Answer VA Final Answer 1 1. The pipe insulation required by Specification Section 23 07 11 is very likely much thicker than the existing insulation. a. Have provisions been made to physically fit the new thicker pipe insulatio...