ATCH 1 SCHEDULE OF ITEMS
Published: 07/25/2012
Description
ENGINEER’S CONSTRUCTION ESTIMATE Massey Branch Boat Ramp Project Revised: July 13, 2012 Page 1 of 5 BASE BID ITEMS: A. PARKING LOT CONSTRUCTION *Pay Item Description Method of Quantity Unit Unit Price A...
