ATTACH 7 QUESTION AND ANSWER.PDF
Published: 10/21/2025
Description
W9127N25QA062, Cole River Substation Questions and Answers Q1. Please clarify the requirement to "reassemble the substation once on site." The substation will be shipped in 3 sections (FJ1, FT1, FQ1) which are typically assembled and installed ...