RESPONSES_TO_QUESTIONS_4
Published: 05/08/2013
Description
Please advise whether the 6 weeks that drawing C1’s general notes (item 19 & 20) mandates for mobilization (3 weeks) and inspection/ testing & commissioning (3 weeks) are part of the 87 days period of performance or not. Answers: The 87 days for th...