ANSWERS_TO_RFI'S_FOR_BIDS
Published: 05/10/2013
Description
Question 1: Plan sheet 3 of 4 RPR Utilities, TLF Site call for "Cured in Place" Pipe liner while the only specification is for Slip Liner. Please clarify which will be used to repair the existing Storm Sewer. Response 1: The line is to be a Cured in ...