RESPONSES_TO_QUESTIONS_-N00421-13-T-0349-0001
Published: 06/12/2013
Description
N00421-13-T-0349-0001 1) Is it possible to complete all the work in two days of field work? I ask, because the biggest challenge will be Task #1 (17 personal air samples), as that will require someone(s) on the facility end to coordinate the work and...