QUESTIONS/ANSWERS #2
Published: 05/16/2014
Description
QUESTIONS AND ANSWERS ROUND 2 RFP 2014-N-15773 QUESTION 1. Should a draft security plan be submitted with the RFP, or should both the draft and final security plans be submitted within 30 days of the contract award? ANSWER: Yes, A draft security Plan...