QUESTIONS AND ANSWERS
Published: 09/17/2014
Description
MAFR Fence Demolition Questions and Responses Revision 1 Dated 17 September 2014 Will there be many days that the contractor will not be able to work due to base operations? Answer: See PWS 1.3. This is unknown at the current time. Interruptions will...