SITE_VISIT_QUESTIONS_ANSWERS
Published: 09/23/2014
Description
FA3047-14-R-0054 - QUESTION AND ANSWERS FROM SITE VISIT 1) Repairing the road after trenching, does the contractor use flowable fill above the concrete encased ducts and then the asphalt? They said that's how they did it at Ft Sam Houston. Answer: No...