RFI
Published: 02/19/2015
Description
RFI’s for FA5270-15-B-0002 Question: What is the governments thinking in mobilizing the project? In phases (10-10-9) or complete one unit and move onto the next? Answer: Since the work is exterior of the building, phasing can be scheduled by the co...