VA244-15-B-0637 A00001 VA244-15-B-0637 A00001.DOCX
Published: 08/04/2015
Description
Renovate 3 North Laboratory Pre-Bid Conference & Site Meeting Minutes 22 July 2015 Introduction: Contracting Officer: Everett Shaver Project Manager/COR: Mike Somoga A&E Firm: S2 Ventures Established rules of communication and the roles of the CO & C...