Q_&_A_-_SITE_VISIT.DOCX
Published: 09/01/2015
Description
SITE VISIT QUESTIONS and ANSWERS (Q & A) 24 AUGUST 2015 REPAIR HVAC, B185, RM 310 Question: The spec book calls for flushing of the new lines. Will chemical treatment/flushing be required on this project? Answer: Flushing with clean water is required...