VA244-16-B-0381 A00002 S02 PRE-BID QUESTIONS AND ANSWERS - PLUMBING DEAD LEG REMOVAL.DOCX
Published: 02/18/2016
Description
Pre-Bid Questions and Answers Question: The specifications state all debris must be removed off site each day. Any option to wait until the roll offs are full? Answer: The VA will require that the site be cleaned before the contractor leaves the job ...