BID TABULATIONS - BID# 17-105 - P-27 CALWOOD CREEK STORMWATER RETROFIT PROJECT - ST. PETERS, MISSOURI
Published: 11/07/2016
Description
Item Description Unity Quantity Unit Cost Cost Unit Cost Cost Unit Cost Cost 1 MOBILIZATION/DEMOBILIZATION LS 1 $10,000.00 $10,000.00 $50,000.00 $50,000.00 $83,421.00 $83,421.00 2 STABILIZED CONSTRUCTION ENTRANCE EA 7 $1,000.00 $7,000.00 $2,000.00 ...