VA262-17-B-0042 A00002 S05-RFIS REPLACE THIRD BOILER.PDF
Published: 12/06/2016
Description
RFIs: Replace Third Boiler VA Long Beach 1. The period of performance for this project is 300 calendar days from the date listed on the Notice to Proceed (NTP). It will take 2-3 months for shop drawings to get approved during the submittal ...