Description
GLEN_15-3303_RFI-07_Sanitary_Sewer_Response.pdf GLEN 15-3303 FA2550-17-R-1016 RFI #7 1. Section 1.2B &1.3 Will Record Drawings be the responsibility of the contractor to produce and provide to the government? Will a PE stamp be required? ...