QUESTIONS_AND_ANSWERS_12-27-17.DOCX
Published: 12/29/2017
Description
QUESTION ONE: Please define “work completion” as it relates to report deliverables time start. ANSWER ONE: Work completion is when all work related to the original work items and negotiated growth work is completed and the engine is ready to start. ...