QUESTIONS AND ANSWERS
Published: 01/10/2018
Description
KS FLAP RS376(1), 19000 Road Bidders Questions: 01/08/2018 Question: Sheet E-10 states that we are only getting 20 days for schedule A and 10 Days for option X. Is this correct? Answer: Schedule A is correct. Option X is 8.5 days due to 4th of Ju...