1 QUESTIONS AND ANSWERS TO RFI’s 1. Q: Conduit and boxes need to be installed above the ceiling in the IH&S trailer, but the ceiling is drywall. Will the contractor be required to demo the ceiling and repair as needed? A: Yes, Ref...