RESPONSE_TO_BQ_0001_REV_1.PDF
Published: 04/10/2018
Description
Question # Document Description Page # Section/ Paragraph Question/ Comment Proposed Action/ Change Government Response 1 RFP 26 Section C-1 / 1 3.3.3.2.1/1 The RFP states “The contractor is fully responsible and provided the design space to d...